Arb RD138 Manuel d'utilisateur Page 24

  • Télécharger
  • Ajouter à mon manuel
  • Imprimer
  • Page
    / 40
  • Table des matières
  • MARQUE LIVRES
  • Noté. / 5. Basé sur avis des utilisateurs
Vue de la page 23
3 Installing the Air Locker
22
3.9 Bench Testing the Air Locker
c To test the Air Locker, when 620kPa [90 PSI] shop air is applied to
the seal housing tube, the Air Locker should engage.
c Check all fittings and the seal housing for air leaks.
c Rotate the differential carrier by turning the pinion flange whilst
applying air pressure.
NOTE : An accurate way to test for air leaks is to fit a shut-off
valve to an air pressure gauge (Available as ARB part
#ALTG01). Charge with shop air until 620 KPA [90 PSI]
is reached, shut the valve off, disconnect the air hose,
and watch to see if there is any drop in pressure. Any
gradual pressure drop indicates an air leak. (Fig.19.)
Figure 19.
c If a leak is found to be present, spray a soap and water mixture
onto the bulkhead air fitting. Bubbles should appear at any leak
points.
NOTE : Do not spray this soapy mixture inside the differential.
c Check that leaky fittings have been adequately tightened.
c Disassemble, clean threads, and reapply thread sealant if leaking
persists.
c If a leak is found at the seal housing, carefully remove and refit. Be
very careful with the O-rings and check they have not been
damaged during installation.